Our Project

ERG_hz+pay_Pant_posProject Status

Site Information

  • Location: Carsphairn, Dumfries and Galloway
  • Status: Appeal submitted in October 2017 to the Planning and Environmental Appeals Division (DPEA) of the Scottish Government.

Facts and Figures

  • Up to 23 MW installed capacity from up to 10 x 2.3MW turbines;
  • Potential to offset around 37,600 tonnes of CO2 each year;
  • 134m to blade tip (80m to hub);
  • Local topography and surrounding woodland will help mitigate visual and landscape impacts on major settlements; and
  • Community Benefit Fund of up to £115,000 per annum, or up to £2.875m over the lifetime of the project.

 